Challenge
- They faced challenges in meeting their client’s requirement of completing the project within a short timeframe added pressure and required efficient project management
- Creating multiple sheets for different phases and maintaining visual appeal and functionality in a large-scale healthcare facility posed a significant challenge
- The client approached us to provide MEP Design and Drafting support for one of their healthcare projects which was comprised of 2 new levels and renovation of existing 1 level with a total of approximately 171,688 BGSF
Our Solutions
- Our team carefully planned the project step by step to ensure timely delivery
- Our team consisted of a MEP engineer and designers with the necessary expertise
- We used Revit 2022 software for modelling ducting and piping routing, incorporating client inputs, and utilizing specialized software like McQuay Duct Sizer and Pipe Sizer for sizing.
- Client feedback was incorporated at various phases, from concept design to final design documentation, to address their requirements and changes
- Our team’s expertise enabled us to overcome challenges in routing pipes and ducts, ensuring clash-free and coordinated MEP design
Results
- Our commitment to quick turnaround times shortened the project timeline from 4 months to 3 months, reducing the duration of the design phase
- A well-coordinated MEP design model enabled the client to cut down the coordination scope with the MEP contractor, leading up to a 20% reduction in the MEP budget cost